Slovensko We Built the Destroyed Part of the Zahišar Homestead -
Main Staps of the Construction


2005, 2 pictures
2006, 27 + 8 (ptk) pictures
2007, 1 picture
2008, 2 pictures
2012, 3 pictures
All of the pictures are 600 x 450 pixels in size,
except the last five (800 x 600 pixels).
Photo and (c) Daniel Rojšek, Danč, 2005-2020.


Božo Before Putting of the Foundation Stone


Here will grow "a nice house"!


Before Starting, the 1st Picture


View on "snag" between the bridge passage and neighboring house, 25th September 2005.


Before Starting, the 2nd Picture


View on "snagged" Goranji Konc, 25th September 2005.


Beginning, the 1st Picture


Izidor was digging with a machine and Igor with a shovel, 5th, January, 2006.


Beginning, the 2nd Picture


"Calm consultation" between Zoran and undersigned, 5th, January, 2006.


Luck Among Felling Marl


During the digging with a machine, due to vibrationa and inclination of fissures around 5 m3 of marl collapsed. Fortunately without consequences.
Situation on the 6th, January 2006.


  • Eight pictures from putting of the foundation stone


    Foundation Plate


    At the end of the month in spite of the severe winter foundation plate was finished, 31st, January 2006.


    The 1st Part of Groundfloor Plate


    In the second half of February under the bridge passage foundation wall was done and the first part of groundfloor plate was finished, 25th, February 2006.


    The 2nd Part of Groundfloor Plate


    The groundfloor plate was finished, 3rd, March, 2006.


    Plate of the 1st Ploor


    The plate of the first floor was finished, 26th, March, 2006.


    Plate of the Loft Space


    The plate of the second floor was finished, Zoran, Osman, Miran and Katja, 13th April, 2006.


    The First Beams


    View to the Zahišar homestead, 11th May, 2006 afternoon.


    Between Sky and Earth


    To work on the roof is not for everyone, 16th May, 2006 morning.


    Roof on Thursday, 18th May, 2006, Morning,
    View Towards Goranji Konc


    Penthouse was covered with bricks painted with large diamonds. Bricks needed to strengthen on the upper side with net and glue, because the roof is occasionally exposed to the storm winds, which in gusts reaching speed more than 200 km per hour. Then the bricks shake and some droped.


    Roof on Thursday, 18th May, 2006 Morning,
    View Towards Sea



    Roof on Saturday, 20th May, 2006 Morning,
    View Towards Goranji Konc


    On Friday insulating plates were covered with water resistant, but breathable fabric.


    Roof on Saturday, 20th May, 2006 Morning,
    View Towards Sea


    Zoran removing planks of the fence that would not be broken by strong wind.


    Roof on Saturday, 4th June, 2006 Morning,
    View Towards Sea


    Bird's view on the roof.
    Photographed by Zoran Simčič.


    Roof on Sunday, 11th June, 2006 Morning,
    View Towards Sea


    New roof is recognised by oval windows below it.


    View Wrom not Covered Subway on Saturday, 24th June, 2006 Afternoon


    Impression of great height of the house beneath the surface of the square is no longer possible.


    View from Street Towards Old Part of the House, Saturday, 1th July, 2006 at Noon



    Goranji Konc, Monday, 10th July, 2006 Afternoon


    There is no more construction pit on the square.


    Subway, 10th July, 2006


    View below the square towards basement of the new part of the house.


    Small Spruce on Thursday, 20th July, 2006 Evening, the 1st Picture


    There is no good construction party without spruce in Slovenija.


    Small Spruce on Thursday, 20th July, 2006 Evening, the 2nd Picture


    Final preparations for construction party.
    View from the window in the roof to the setting sun.


    Closed Windows and Entrances on Sunday, 22th July, 2006 Evening,
    the 1st Picture


    Katja and me closed windows in groundflor and entrances after the party.
    View to the lower part of the house.


    Closed Windows and Entrances on Sunday, 22th July, 2006 Evening,
    the 2nd Picture


    View to the upper part of the house.
    A little rest was valuable.


    The First Stone Window Frames


    Too much rest can also be harmful.
    The frames arrived at the end of the year 2006, the first were in place on 28th May, 2007.


    All the Frames in Place


    The last arched part of the framework was in place on Friday 20th July, 2007.


    Rock Wool


    In a little while house would be "dressed" in the 8 cm thick layer of rock wool, Friday, 8th February 2008.


    Plaster


    Walls were covered with breathable lime plaster, Thursday, 13th March, 2008.


    New Floors - the First Picture


    At Goranji Konc, Saturday, 29th June, 2012.

    New Floors - the Second Picture


    At the lower street, Saturday, 29th June, 2012.

    New Floors - the Third Picture


    View from the lower street through bridge passage to the Goranji Konc, Saturday, 29th June, 2012.



    The page from 2nd March, 2013 by Daniel Rojšek.
    Your comments are welcome.

    In your e-mail application ... is to be changed to @.
    This web intruders do not know, yet.

    Date of last change: 4th June, 2020.

    URL: http://dar.zrsvn.si/opr/brda/zdb/psg-en.html